ISS Assembly


   

20.11.1998
Launch of the Zarya Control Module with a Proton rocket.

   

04.12. - 15.12.1998
The crew of STS-88 docks the Unity node to the ISS.

   

27.05. - 06.06.1999
Nearly 2 tons of equipment were brought to the ISS and the Canadian built manipulator arm were mount by the crew of STS-96.

   

19.05. - 29.05.2000
The crew of STS-101 installed the final parts of the Russian built crane.

   

12.07.2000
The Zvezda Service Module launched atop a Russian Proton rocket and docked to the Station two weeks later.

   

08.09. - 20.09.2000
STS-106 completed final connections (electrical-, data- and television cables) between Zvezda module and component Zarya.

   

11.- 24.10.2000
The crew of STS-92 attached the docking port, called Pressurized Mating Adapter 3 (PMA-3).

Expedition 1

 

01.- 11.12.2000
Attaching of the P6 solar array structure by the crew of STS-97.

 

07. - 20.02.2001
The crew of STS-98 docked the Destiny lab.

Expedition 2

 

08. - 21.03.2001
STS-102: PMA-3 repositioned from the berth to the port side of Unity to make room for Italian built Multi-Purpose Logistics Module "Leonardo".

 

19.04. - 01.05.2001
Installing of the Canadian built robotic arm (57.7 foot long) called Canadarm2 by the crew of STS-100.

 

12. - 25.07.2001
The crew of STS-104 attached Joint Airlock Module ("Quest").

Expedition 3

 

10. - 22.08.2001
Ammonia servicing unit and two science experiment packages attached by the STS-105 crew.

Expedition 4

 

05. - 17.12.2001
STS-108 brought three tons of supplies with the MPLM Raffaello cargo module.

 

08. - 19.04.2002
Integrated Truss Structure S0 and Mobile Transporter attached by the crew of STS-110.

Expedition 5

 

05. - 19.06.2002
Installation of the second component of Canada's Remote Servicing System to the ISS (STS-111).

 

07. - 18.10.2002
The crew of STS-112 attached the Star-board One (S1) Truss and the first (SO) Truss segment.

Expedition 6

 

24.11. - 07.12.2002
P1 solar array truss segment attached by the crew of STS-113.

Expedition 7

     

Expedition 8

     

Expedition 9

     

Expedition 10

     

Expedition 11

 

26.07. - 09.08.2005
Installation of the External Stowage Platform-2 Attachment Device (STS-114).

Expedition 12

     

Expedition 13

 

04. - 17.07.2006
The crew of STS-121 brought supplies with the MPLM cargo module.

 

09. - 21.09.2006
The crew of STS-115 installed the P3/P4 integrated truss and the solar arrays.

Expedition 14

 

10. - 22.12.2006
P5 truss segment attached (STS-116).

Expedition 15

 

08. - 22.06.2007
Installation of the S3/S4 truss by the crew of STS-117.

 

08. - 21.08.2007
S5 truss attached (STS-118).

Expedition 16

 

23.10. - 07.11.2007
The crew of STS-120 attached the Node 2 ("Harmony").

 

07. - 20.02.2008
European Columbus module attached by the crew of STS-122.

 

11. - 27.03.2008
The crew of STS-123 attached the Japanese Experiment Module ("Kibo") and the Canadian built Special Purpose Dexterous Manipulator ("Dextre").

 

03.04.2008
Arrival of the ESA built Automated Transfer Vehicle (ATV)

Expedition 17

 

31.05. - 14.06.2008
The JEM PM and the JEM RMS was attached by the crew of STS-124.

Expedition 18

 

15. - 30.11.2008
The crew of STS-126 brought with MPLM Leonardo supplies and equipment to the ISS.

 

15. - 28.03.2009
ITS-S6 attached by the crew of STS-119.

Expedition 19

     

Expedition 20

 

15. - 31.07.2009
The JEM EF, JEM ELM-ES was attached by the crew of STS-127.

 

29.08. - 12.09.2009
The crew of STS-128 brought with MPLM Leonardo supplies and equipment to the ISS.

 

17.09.2009
Arrival of the JAXA built HTV

Expedition 21

 

16. - 27.11.2009
ELC-1 ELC-2 attached by the crew of STS-129.

Expedition 22

 

08. - 22.02.2010
The crew of STS-130 attached the Tranquility node and the Cupola.

Expedition 23

 

05. - 20.04.2010
The crew of STS-131 brought with MPLM Leonardo supplies and equipment to the ISS.

 

14. - 26.05.2010
ICC, MRM-1 (now Rassvet), ERA attached by the crew of STS-132.

Expedition 24

     

Expedition 25

 

Expedition 26

 

24.02. - 09.03.2011
ELC-4 attached by the crew of STS-133.

Expedition 27

 

16.05. - 01.06.2011
ELC-3 and AMS attached by the crew of STS-134.

Expedition 28

 

08. - 21.07.2011
The crew of STS-135 brought with MPLM Raffaello supplies and equipment to the ISS.

 

Expedition 29

     

Expedition 30

     

Expedition 31

     

Expedition 32

     

Expedition 33

     

Expedition 34

     

Expedition 35

     

Expedition 36

     

©        
Last update on May 14, 2013.