close window |
Total EVAs: | 2 | ||
Total EVA time: | 13h 17m |
No. | Date | Together with | Time | Main tasks and notes |
1 | 15.01.2003 | D. Pettit | 6h 51m |
Continuing outfitting and activating the
International Space Station's newest component, the P1 (P-One) Truss and
relocating a toolbox from the Z1 Truss to one of the Crew and Equipment
Translation Aid. |
2 | 08.04.2003 | D. Pettit | 6h 26m |
Reconfiguring power connections, providing a
second power source for one of the Station's control moment gyroscopes,
securing thermal covers on quick disconnect fittings for the station's thermal
control system and to get a latch unstuck, which holds down a support for a
light on the Crew and Equipment Translation Aid (EVA)
carts. |